|

2003 Archive

Thursday,
November 06, 2003
Utility district
considered for New London and township
By Carolyn Lange,
Staff Writer
NEW LONDON -- The
possibility of creating a utility district that would be operated jointly
with New London and New London Township could be explored. The two entities
will be meeting next Thursday to listen to an expert in the field of
utilities districts.
Providing utilities has been an issue as the two entities debate
annexation.
After a defeated attempt to merge the communities, the township and city
have been trying to iron out an orderly annexation agreement, while at the
same time trying to accommodate township residents who want water and sewer
services, but don’t necessarily want to be annexed.
The city and township are currently working together to bring utilities
to a developer in the township. It’s understood that the property will be
annexed, even though it’s not contiguous with the city boundary and
by-passes an existing residential development that doesn’t want to be
annexed.
At their meeting Wednesday, the Council briefly discussed options for
continuing their negotiations with the township and if creating a utility
district would enhance future growth for the city.
In other action the council:
- Agreed to send a message to the Green Lake Sanitary Sewer and Water
District board that they should cut their budget to prevent deficit
spending. The GLSSWD’s proposed 2004 budget shows a deficit of $32,300.
The Council said cities and townships had to cut budget because of
cut-backs, and the GLSSWD should do the same, rather than spend down the
reserve fund.
- Approved revisions to several ordinances, including extending the
curfew hours. Currently the curfew for juveniles is from 10 p.m. to 4 a.m.
With the change, the curfew will end at 6 a.m.
- Delayed action on the personnel committee’s recommendation to provide
a 2 percent across the board salary increase for the city’s three
employees. The recommendation also included a $50 per month increase in
the employee benefit allotment, which is given instead of health insurance
coverage.
|
Thursday, November 06, 2003
Road stays closed
but party goes on
By Carolyn Lange,
Staff Writer
SPICER -- Cold,
snowy weather will delay the opening of state Highway 23 to Spicer by
another week, but the party to celebrate the end of the detour will go on
tonight as planned.
The Minnesota Department of Transportation had planned to open the 1-1/2
mile section of new four-lane highway today or Friday. Those plans had to be
scuttled because inclement weather prevented necessary painting of road
stripes to be completed.
Paul Jurek, MnDOT construction engineer, said the remaining painting
needs to be done on U.S. Highway 71, where traffic has been detoured while
the new four-lane state Highway 23 was constructed. He said the yellow
stripes need to be removed and new white lines painted.
In order for that to happen, the weather needs to warm up to about 40
degrees. “It’s got to be warm and dry,” he said. “The forecast has been
switching around on us a little bit.”
Jurek said as soon as there’s a “window of opportunity, we’re going to
jump on it quick and open it” so Highway 23 can be opened this fall.
Ending the detour can’t come soon enough for Spicer businesses and
residents. The Spicer Economic Development Authority, Commercial Club and
Duininck Bros. Construction are hosting a “destroy the detour” party from
5:30 to 7:30 tonight at Melvin’s on the Lake.
“We felt the community needed to be told the detour is officially behind
us, even though the weather didn’t cooperate,” said Dave Baker, from the
commercial club.
“We’re telling people the road will be open and it’s going to be a
beautiful road,” said Baker.
While traffic flowed through town this summer during the construction,
Baker said it appears some businesses suffered more than anticipated this
fall as people by-passed Spicer on the detour.
“We want to make sure folks in the 25-mile radius know there won’t be a
detour and a delay any more,” said Baker.
At the party, Jurek will give a short presentation about the project to
date and what can be expected for construction this winter -- which includes
a detour as the Nest Lake Bridge is replaced -- and next year as the project
progresses north past New London.
The total four-lane project is about 11 miles. Segments of it may not be
completed until 2005.
Jurek said he intends to “thank everyone for their patience” during the
project and thank drivers for keeping the project safe for construction
workers. He said the project did receive a Work Zone Safety Award.
The Highway 23 celebration is free and open to the public. Maps of the
project will be available and Jurek will be there to answer questions.
|
Thursday,
October 30, 2003
Highway 23/71
interchange expected to open next week
By Carolyn Lange, Staff Writer
SPICER --
Plans are in the works to celebrate the reopening of state Highway 23 from
Willmar to Spicer next week.
Weather permitting, the Minnesota Department of Transportation intends to
open the 1½-mile stretch of new four-lane, and the new Highway 71/23
interchange, on Thursday or Friday of next week, according to Paul Jurek, MnDOT
construction engineer. The detour, and temporary stoplight on U.S. Highway 71,
will be removed at that time.
The new overpass with County Road 9, off of Highway 23, won’t be open for
another two weeks.
One segment of the massive highway project was completed Wednesday when the
newly realigned County Road 10 was opened to traffic in Spicer. The road creates
a new four-way intersection with Highway 23 at Mel’s Sport Shop.
The intersection will be controlled by a stop sign on County 10 until next
fall, when a stoplight will be installed. Getting the county road completed was
a “big thing for Spicer,” said Jurek. Opening Highway 23 to Spicer, however,
will come later than planned.
Jurek said the goal to complete the Highway 71/23 interchange by Friday fell
through because of the recent cold, wet weather, said Jurek. Crews were unable
to finish painting lines on the road. Delaying the opening will allow workers to
finish up some other odds and ends, like erecting signs.
The newly completed four-lane begins at the Highway 23/71 divide by Willmar
and continues to just north of County Road 9. Although the additional lanes for
the four-lane have been built through Spicer, they won’t be open for traffic.
Next spring, all traffic will be shifted to the new lanes while the existing
lanes are rebuilt.
Members of the Spicer Commercial Club, Economic Development Agency and city
office will be meeting with MnDOT and Duininck Bros. Construction on Friday to
discuss details for a ribbon-cutting ceremony that will be held when the road is
opened to traffic.
Dave Baker, commercial club president, said the community wants to celebrate
the return of the vital transportation “artery” that brings people to Spicer.
Crews also intend to complete the frontage road by the Dairy Queen next week.
Jurek said the water retention pond at the former Food-N-Fuel site is being
excavated this week and will be functioning at partial capacity this fall.
Some form of construction will continue on the remaining 11-mile project
throughout the winter. Jurek said that grading will continue until Thanksgiving
and that storm water pipes will be installed through the end of December,
weather permitting.
Work will begin in February to replace the Nest Lake Bridge. Road
construction will resume next spring on the northern portion of the four-lane
project, which extends past New London.
Wednesday, October 19,
2003
County recommends split detour on Hwy. 23
By Linda
Vanderwerf, Staff Writer
WILLMAR -- The
Kandiyohi County Board has recommended a split detour on state Highway 23
during Nest Lake bridge construction next year.
The board met Friday morning to discuss road and bridge issues.
The board voted to ask the Minnesota Department of Transportation to
detour truck traffic around the Nest Lake project by sending it north on
U.S. Highway 71 and east on County Road 40 through New London.
A second, shorter detour was recommended for cars and construction
traffic. They would follow Highway 23 through Spicer, travel west on County
Road 30 and then north on County Road 131 and back to Highway 23. County
Road 131 is also known as the Old Mill Road.
The detour is expected to begin on Feb. 1 and last about 10 months.
Several Old Mill Road residents said they were concerned about the amount
of traffic they’d see if all the highway traffic was detoured on their road.
The road doesn’t have shoulders in some areas and isn’t strong enough to
hold up to heavy trucks, they said.
“If an emergency vehicle comes along, there’s no place to pull off,” said
resident Ron Schmitz.
Ann Latham, who said she uses County Road 30 every day, suggested County
Road 40 would be a better option.
MnDOT project engineer Paul Jurek said New London residents had objected
to using County Road 40 because traffic would run in front of the school.
MnDOT officials had considered the possibility of a separate detour for
truck traffic.
“I think that’s a great idea,” said Commissioner Richard Falk of Willmar.
Commissioner Dennis Peterson of Spicer, who represents the Highway 23
area, said he would be more comfortable “dividing up the load” with two
detours.
“Everybody might be angry if they have to share it, but that seems to be
the fairest way,” Peterson said.
The county could sign an agreement with MnDOT for road maintenance and
repairs during the detour. However, the state could use the detours even if
the county didn’t agree, said county Public Works Director Gary Danielson.
In other business, the board:
- Approved the drainage plan for the Mills Fleet Farm site south of
Willmar along Highway 71. Runoff from the site will drain into a retention
pond capable of holding the rain from a 100-year storm. The pond is
designed to release the water in a county ditch gradually, so landowners
downstream won’t be affected.
A representative of Mills said the company has all its permits in line
and was ready to award contracts to begin work on the complex, which will
include a large retail store, an auto dealership and a convenience store.
- Discussed problems residents in the eastern part of the county had
with R & G Construction of Marshall. The company has the contract to make
improvements on County Road 10.
Danielson said the company’s crews did a good job building the road.
However, the company frequently cut phone lines and drove on crops planted
outside the construction right of way, he said. Crews have also been
called back several times to finish all the work on the job.
In the future, the county will provide much more specific
specifications in contracts, spelling out all the work that needs to be
done to complete a project, Danielson said.
|
Monday, October 6, 2003
Crews strive to finish south part of Hwy. 23 project before winter
By Carolyn Lange,
Staff Writer
SPICER --
Construction crews working on the state Highway 23 four-lane project are
trying to finish up segments on the south end of the project before snow
flies. At the same time, initial preparations have begun on the north end of
the 11-mile project, where highway construction will continue next spring.
Work on two overpass bridges that connect Highway 23 with U.S. Highway 71
and Kandiyohi County Road 9 is nearing completion, said Lee Duininck, from
Duininck Bros. Construction, the contractor for the project. He said the
Highway 71 bridge is “nearly done” except for a few odds and ends and that
the Highway 9 bridge is “coming along pretty well.”
Even though construction of the two overpasses should be completed by the
end of October, the road won’t be opened until all the guard rails and signs
are erected. Duininck predicted that wouldn’t happen until November.
Four lanes of traffic will be open from Willmar to just west of County
Road 127, said Paul Jurek, construction manager from the Minnesota
Department of Transportation. Traffic will then travel on the existing two
lanes going through Spicer, even though the two new additional lanes will be
paved.
Getting the project completed on schedule depends on how fast winter
arrives.
“Every day of good weather helps us,” said Jurek. “We’d like to see
everything get done, but at some point we’ll have to close everything down
and button up for the winter.”
Duininck said rainy weather this spring put a clinker in the construction
schedule. “It’s hard to make up when you had six weeks of rain,” he said.
“We’re behind schedule a little bit.”
There are a number of construction spots that need to be tidied up before
winter, and Duininck said steady progress is being made on those areas. He
said underground work will be completed by Monday or Tuesday on County Road
10, which is being rerouted to a new path in Spicer. That road will be open
for traffic this fall, he said.
Jurek said some areas in Spicer are getting final touches. Roads are
being paved and grass is being seeded. “Everything’s coming together good in
Spicer,” he said.
While it’s easy to see progress as the new lanes of traffic begin to take
shape, there’s considerable work that takes place before that happens, said
Jurek.
Underground utilities and retaining walls in areas along the Woodcock
Addition and Nest Lake need to be completed before road beds are made
“That’s an area we want to get shaped up before winter,” said Jurek.
“There’s a lot of work to do there yet.”
Removal of the old Our Lady of the Lakes Catholic Church, which is
located where a large storm water retention pond will be built, is expected
to take place sometime this month.
Originally, the vacated church was supposed to have been moved off the
property by Oct. 1. That deadline was extended because assessment and
abatement of hazardous materials wasn’t completed in the building.
Tom Key from Advanced Environmental Restoration said aside from asbestos
in the floor tiles and some “odds and ends,” there wasn’t a lot of hazardous
materials to be removed from the structure.
Key said his crews should be done by Monday or Tuesday. After the
environmental all-clear is given, the building can be moved. Al Peterson of
rural Sunburg purchased the church, which was built in three segments over
the years. Peterson said he intends to make three separate homes from the
church.
Duininck said getting the church moved soon is important. “We urged them
to get in there as fast as they could.”
This week, construction crews started moving north, toward New London.
Several houses and piles of trees were burned along Highway 23. Some utility
poles will be moved and the hilly terrain will be graded down to make the
area ready for spring construction, said Jurek.
In February, crews will begin working on the new Nest Lake bridge,
necessitating a detour that’s expected to last about nine months.
Last month, Jurek told the New London City Council that truck traffic
from Highway 23 would be routed through New London during construction of
the bridge. Car traffic would be detoured onto County Road 30 -- known
locally as the Old Mill Road -- and County Road 131, located near Jimmy
Apple Seed. That plan may be changing.
Jurek said MnDOT is now considering detouring all traffic onto County
Roads 30 and 131. This detour would add a mile or so onto the route, as
opposed to six to seven miles by going through New London on state Highway 9
and over to Highway 71.
Trudie Dubord, New London city clerk, said the council isn’t keen on
having extra truck traffic detoured onto the town’s Main Street. She said
the new detour plan would be welcome news. Jurek said no firm decision has
been made.
“It’s not cut in stone yet,” said Jurek. “We’re working on it to get
everyone’s viewpoint.” He said a decision would be reached before work on
the bridge begins in February. |
Monday, September 8, 2003
Dry weather good for road
construction
By Carolyn Lange,
Staff Writer
 |
 |
 |
 |
 |
Tribune
photo by Bill Zimmer
Work crews pour cement Friday to create a wall for the holding pond
along state Highway 23 in Spicer, at the former site of George’s
Food-N-Fuel. |
 |
 |
SPICER
The dry summer has been bad for crops but good for road construction.
The last two rainless months have helped crews on the state Highway 23
project through Spicer gain ground after falling behind schedule during the
wet spring.
Although workers have been steadily inching their way down the 11-mile
construction zone, the project isn’t quite where it should be, said Paul
Jurek, construction engineer with the Minnesota Department of
Transportation.
“We’re getting close to being back on schedule, but we’re still a little
behind in some areas,” he said. “If the weather holds, I think we’ll be just
fine.”
Heavy and continuous rains were a problem early this spring and put the
construction anywhere from two to four weeks behind schedule, said Jurek.
July and August provided “good road building weather,” he said. “A lot’s
been accomplished in the last two months, but we’ve needed it to get back on
track ... there’s so much to do.”
Priority areas on Highway 23 that should be completed on time include the
overpasses and high exchanges with U.S. Highway 71 and Kandiyohi County Road
9. Jurek said those segments are scheduled to be completed by Oct. 31. “That
portion is on target,” he said.
Installation of underground utilities and construction of the water
retention pond at the old Food-N-Fuel site has gone slower than expected, in
part because of the wet spring, said Jurek.
Last week, crews began pouring a 16-foot-high concrete retaining wall by
the pond. All but 2 feet of the wall will be underground, said Jurek. The
wall will be painted to have a simulated rock look. It’ll be topped with an
anti-graffiti coating.
The wall will be poured in six different segments, with each segment
taking several days to complete. Once the wall is completed, then the pond
will be dug. Jurek said part of the wall and pond won’t be completed until
next year.
Although the dry weather has been welcome, Jurek said even the road crews
wouldn’t mind seeing a little rain. Every additional day without rain means
the construction schedule can advance, but it also “means it gets dustier
out here,” he said. “We could use a little rain to settle the dust.”
An update on other portions of the project:
- Crews removing hazardous materials from buildings along the Highway 23
corridor are nearing completion, with about 10 buildings remaining,
including the Catholic church, which should be completed in September. The
church will be moved off the site by mid-October and construction of a
water retention pond will begin.
- About half of the box culvert for the recreation trail has been
installed.
- Additional wetlands have been constructed to replace wetlands that
have been filled in.
- Edge drains that will tile water run-off will be installed during the
next week in Spicer.
- More curb and gutter will be installed by the end of September.
Jurek said crews will continue to move north towards the Nest Lake
Bridge. Work on the bridge, including pounding in pilings, could continue
through the winter. Most of the construction will, however, shut down this
fall. |
|
|
Saturday, July 19, 2003
Lake Avenue and
Ruth Street in Spicer to reopen
SPICER -- Lake
Avenue and Ruth Street in Spicer, near Mel’s Spot Shop and the former
George’s Food-N-Fuel site, will reopen to traffic on or before Monday.
Paul Jurek, construction engineer with the Minnesota Department of
Transportation, said the road may be paved and open to traffic this weekend,
weather permitting. The two streets have been closed since July 10 for storm
and sewer utilities installation.
Miller Street and Lake Avenue remain closed to traffic for storm sewer
installation. Watch for changeable message signs showing alternate routes.
For information related to the state Highway 23 project, log onto the
project website at
http://www.dot.state.mn.us/d8/projects/23/. |
Thursday, July 10, 2003
Spicer
council discusses street and utility projects
By Carolyn Lange,
Staff Writer
SPICER -- How to
construct, and pay for, two costly street and utility projects was discussed
Wednesday by the Spicer city council.
The council approved plans to install new water and sanitary sewer lines
under state Highway 23 to the Woodcock Addition, at a cost of $250,890.
That quarter-of-a-million dollar project will be done by Duininck Bros.
Construction of Prinsburg as a change-order to the Highway 23 four-lane
project. Work could begin in the next few days.
The council also agreed to call for bids to bring the utility lines to
the 20 or so homes in the Woodcock Addition and rebuild the streets there.
That part of the project is estimated at $400,000, for a total cost of
$661,000.
“This is a high-risk, difficult project,” said City Engineer Randy Sabart.
The council decided earlier it made sense to have Duininck Bros. install the
lines under Highway 23 at the same time it was building the four-lane road.
The council could reject bids for the second part of the project if the
cost is too high, but that would make it difficult for the city to assess
homeowners for the initial utility work, said Mayor Bill Taylor.
Councilman Troy Block said he believes homeowners in the area want the
project and are prepared for the assessments. Bids will be let Aug. 5.
Two business owners located in Progress Circle, however, told the council
they didn’t want to pay high assessments for a project proposed in that
area.
During a public hearing, Sabart said plans to build a 32-foot road with
curb and gutter and to install an adequate drainage area for the nine
commercial parcels would cost about $220,000. The proposed assessments range
from $37,000 to $68,000 per parcel.
Lenny Chapin from West Central Insulation said the project was
“over-kill” and the cost too high.
The “lion’s share” of the cost, said Sabart, is to dig a sediment pond
and create appropriate drainage routes for storm water. That portion is
estimated at $163,000.
Sabart said representatives of the Department of Natural Resources and
Kandiyohi County Environmental Services have said storm water cannot be
channeled to an existing wetland in the area. Instead, a man-made sediment
pond would have to be built as part of the plan.
Taylor said the city’s actions are “dictated” by state regulations.
As a businessman, Chapin said he’s dictated “by the pocketbook.”
The idea of spending so much money to dig a pond was “ridiculous,” said
Chapin, who asked the council to look for different options. Craig Shuck,
from Beaver Masonry, said the drainage benefit “ain’t worth that kind of
money.”
Since commercial development in Progress Circle has expanded, storm water
has caused erosion of ditches and the current minimum-maintenance road, said
Taylor.
According to council members, most of the drainage problems were created
when two businesses, the Twin Spin Theater and G. Michael’s’ restaurant,
expanded without installing an adequate storm water system. The council has
been trying to work out a solution with the property owners for more than a
year without success.
“It’s been a little bit of a battle with the property owners,” said
Councilman Jerry Reierson, adding that some of the property owners “don’t
give a darn” about fixing the problem, which is forcing the city to take
action and pass on the costs to all the property owners. “We’re trying to
solve a mess up there.”
Councilwoman Marlys Larsen said the businesses that benefit the most from
the project should be assessed more. Sabart said, however, assessment
policies need to be consistent and fair.
Council members agreed to reconsider the project at their next meeting.
In other action the council:
- Discussed an emergency meeting held June 25, that was attended by
three council members to discuss liability and actions of the Minnesota
Department of Transportation and Duinincks following heavy rains that
caused dirty water to go into Green Lake. The meeting was held at the
request of Councilwoman Larsen.
Reierson said when he was called and asked if a meeting was necessary,
he said no, and wasn’t informed the meeting was going to be held. The
press was also not notified of the meeting. Taylor was out of town.
- Told the owners of O’Neils that if they wanted to keep their bar open
until 2 a.m. they’d have to apply to the state. The council would then
sign off on the permit.
- Held a closed meeting to discuss litigation regarding a claim made
against the city.
|
Thursday, June 26, 2003
Heavy
rains stress erosion-control measures on Highway 23
By Carolyn Lange,
Staff Writer
SPICER --
Erosion-control measures were being reinforced Tuesday along the state
Highway 23 four-lane construction project, following heavy rains Monday.
Amounts vary, but it’s estimated that Spicer received more than 3 inches
of rain Monday, including about 2 inches in a half-hour. The deluge, after a
weekend of rain, caused flooding in the highway construction area, resulting
in dirty water flowing into Green Lake.
With more showers in the forecast, officials from Duininck Bros.
Construction and the Minnesota Department of Transportation held a meeting
Tuesday to assess areas where preventative procedures succeeded and failed
and to develop a plan for implementing corrective measures.
Crews repaired washed out areas and installed more silt fences and other
measures to restrict and clean any additional storm water, said Rodney
Hughes, erosion control supervisor for Duinincks. “We’re beefing up
security,” he said.
Bob Miesen, a member of the Lake Region Preservation Society, said he
watched plumes of “filthy” water enter Green Lake on Monday. He said the
scene was “what we fought so hard to avoid.”
“It confirms our worst nightmares,” said Pat Laib, another member of the
preservation society who’d served on a water quality advisory committee that
helped create a plan for preserving area lakes during and after the
construction project.
Laib said he and other committee members repeatedly asked about the
effects a heavy rain would have on the project, without getting a good
response. “We’ll get the road, but we’ll lose our lake.”
Miesen said he called the Army Corps of Engineers and the lieutenant
governor’s office Tuesday morning to request that the construction project
be stopped until an environmental impact statement was completed.
“It’s common sense that the project be stopped and re-evaluated,” said
Miesen, adding that an EIS should’ve been done before the four-lane corridor
was selected.
Paul Jurek, MnDOT construction manager, said the corps told him on
Tuesday the project would not be shut down, but they wanted to know what
remedial efforts were being taken.
Jurek said the heavy rain was “not what we were hoping for” and that
MnDOT and Duinincks were “addressing as much as we can” to prepare for more
rain that could stress erosion-control measures even further.
Hughes said there were problems with erosion, but that in about 85
percent of the construction area, erosion-control measures worked very well
Monday. An area where it failed was by Mel’s Sport Shop, where waist-high
water pooled in a street that was under construction.
The rain water flooded the city’s manholes and sanitary sewage lift
station, said Dan Haats, Spicer’s public works director. Without fast
action, Haats said raw sewage would have flowed onto the street and into
Green Lake and flooded homes.
Crews pumped the muddy, gray rain water from the street into Green Lake
for about four hours, said Haats. “That was the only course of action they
could’ve taken, was to pump it into the lake.” Sewage did back up in about a
half-dozen basements, said Haats, but it would’ve been worse if the pooled
rainwater hadn’t been pumped out of the street.
Hughes said pumping dirty water into Green Lake was a “last resort”
measure. “Nobody wants any dirty water going into any lake,” he said.
Crews did “everything we could do” to prevent erosion, Hughes said, but
getting so much rain in such a short period of time was too much for any
system to handle. Hughes said even without the highway construction, there
would’ve been some erosion and dirty water would’ve flowed into Green Lake.
Road construction will likely be stopped for the rest of the week,
especially if there’s more rain, said Jurek. That will put crews behind
schedule for completing segments of the project in time for Spicer’s Fourth
of July celebration. Jurek said they’ve “moved to plan B,” and that routes
are being prepared for the parade. |
Tuesday, June 24, 2003
Storms pass through region
By Michael
Benedict, Staff Writer
 |
 |
 |
 |
 |
Tribune
photo by Bill Zimmer
Dan Commerford, owner of Green Lake Nursery in Spicer, tries to open
drains Monday afternoon heavy rains hit the Spicer area, causing flash
flooding. |
 |
 |
At least three
tornado warnings were triggered late afternoon and early evening Monday when
a line of thunderstorms passed through the region.
One rotating storm was spotted in the clouds by National Weather Service
radar in the New London-Spicer area.
“The National Weather Service reported a tornado in the clouds,” said
John Edwards, a local storm spotter. “I didn’t have any indication of any
rotation.”
The other warnings were reported in Renville County near Hector, but no
reports of structural damage from these storms were made to the Renville
County Sheriff’s Department by 8 p.m.
The Renville County warnings were issued after storm spotters noticed
wall clouds north of Hector, according to the department. Rainfall there was
reported as showers.
There was, however, significant rainfall in Spicer, with one report of
3.7 inches.
The Spicer rainfall prompted a handful of telephone calls to the Tribune
after the storm.
People were upset after the storm that runoff from highway construction
was pouring into Green Lake in Spicer, said Marlys Larsen, a member of the
Spicer City Council. City residents were earlier assured that runoff from
the transformation of Minnesota Highway 23 into a four-lane highway wasn’t
going to reach the lake, she said.
“It’s flowing directly into the lake,” Larsen said. “A lot of people did
not want this four-lane. It (the lake) is one of our prizes.”
An owner of the company that is building the four-lane road, however,
said there is nothing that would prevent such runoff after such heavy
rainfall.
“There is no choice when you get 3.7 inches of rain in an hour,” said Lee
Duininck of Duininck Bros. “The people who are calling are right. If anyone
has any ideas (on how to prevent the runoff), I would like to know.”
As required by the Minnesota Department of Transportation, Duininck said
retention ponds are constructed as the project progresses.
Other area rainfall amounts during the storm included 1.30 inches in
Willmar in about 45 minutes and 2.5 inches in New London in about one hour.
Several intersections were left flooded in Willmar after the storm, and
reports of hail were also reported in different areas of Kandiyohi County.
|
Saturday, June 14, 2003
Business owners say
don’t fear road to Spicer
By Carolyn Lange,
Staff Writer
SPICER --
Cowardly-lion travelers may discover it takes less courage than they think
to follow the road to Spicer. Despite major construction of a four-lane,
state Highway 23 is open through Spicer and so are the businesses in town.
To let people know Spicer is open for crucial summertime business, the
Spicer Commercial Club is launching a marketing campaign next week based on
the Wizard of Oz. Ads and billboards will encourage folks to follow the
ever-changing, yellow-brick construction road to Spicer.
The Spicer Commercial Club, with financial donations from the New London
Chamber of Commerce and the cities of Spicer and New London, will be running
the marketing campaign for the two-year duration of the construction
project, said Dave Baker, president of the commercial club.
Baker said businesses from both Spicer and New London decided they needed
to have a proactive role in telling people that Highway 23 is open and that
“this area is very much open for business. There will never be a detour
around Spicer.”
Unfortunately, he said, some people assume there are big detours and that
Spicer is hard to get to. “Some people exaggerate what they’ve seen and say
‘you can’t go to Spicer, it looks like Baghdad.’”
Baker, who owns a restaurant and hotel in Spicer, said the road through
town is actually in good shape, signs direct travelers to streets to access
businesses and the hassle is minimal. “You should go see it for yourself,
it’s not so bad,” he said.
Backhoes, gravel trucks and construction crews aren’t the main thing
that’s slowing down traffic in Spicer, said Spicer Economic Development
Director Jean Spaulding. “It’s gawkers, like me,” she said with a laugh.
With trees being removed, hills being cut away and new roadbeds created
for the future four-lane, the landscape can change from the beginning of the
day to the end. Even for people like Spaulding, who can watch the
construction from her office window, the daily changes are incredible.
“If they haven’t been here, they’d be totally amazed at how things have
changed so quickly,” said Spaulding. “But there’s a misconception out there
that you can’t get through Spicer, and that’s not true at all.”
The Minnesota Department of Transportation and the contractor, Duininck
Bros., have agreed to always keep a road open through Spicer during the
two-year construction project. Sometimes traffic will be diverted to a
side-street, but Spicer will be always be accessible.
Baker praised MnDOT and Duinincks for working closely with businesses on
the construction project to minimize the negative impact to businesses.
As a business owner, Baker said, “there’s nothing more frustrating than
seeing the road closed in front of your business,” but he said MnDOT and
Duinincks have “done an exceptionally good job of keeping the roads open as
long as they can.”
So far, Baker said local companies are reporting that the summer business
is about the same as last summer. He said by telling people that the highway
is open, those business will still be open in two years, when the
construction is done. |
Wednesday, June 11, 2003
Erosion control crucial
to highway project
By Carolyn Lange,
Staff Writer
 |
 |
 |
 |
 |
Tribune
photo by Carolyn Lange
Silt fences and a rock berm keep storm water and erosion in check along
the state Highway 23 construction zone. The primary contractor, Duininck
Bros. of Prinsburg, is required to have a certified erosion control
supervisor on staff and on the site. |
 |
 |
SPICER -- The
environmental sensitivity of the four-lane expansion of state Highway 23
through Spicer has brought about a “first ever” in road construction in the
state.
The 11-mile project is required to have an erosion control supervisor
on-site during the two-year construction process. It’s the first time the
Minnesota Department of Transportation has made such a requirement,
according to MnDOT officials. Because of a new emphasis on erosion
prevention in the state, it’s likely the beginning of a trend.
The Highway 23 project is environmentally critical be-cause of its
proximity to Green, Nest and Eagle lakes and numerous wetlands, said Paul
Rasmussen, MnDOT hydrologist. “The project was also extremely complex, which
warranted additional measures to take care of that.”
As a result, MnDOT required the primary contractor, Duininck Bros. of
Prinsburg, to have a certified erosion control supervisor on staff and on
the construction site to coordinate all the erosion-control activities, said
Rasmussen.
Rodney Hughes is one of a half-dozen Duininck’s employees who underwent
special training at the University of Minnesota, specifically for the
Highway 23 job. As erosion control supervisor, Hughes has some serious
responsibilities.
Just two months into the project, about $2 million has been spent on
erosion control measures, said Hughes. If something goes wrong, “the state
has the power to fine me on-site.”
Hughes keeps in constant communication with the subcontractors and makes
sure the erosion-control measures are being installed correctly and are
working like they’re supposed to. Besides regular inspections, within 12
hours of a rainfall, Hughes views the sites, determines if corrective action
is needed and fills out another page on an official Minnesota Pollution
Control Agency storm water log.
A tour down the construction corridor with Hughes reveals progress is
being made on the 44 permanent storm water retention ponds scheduled to be
built in conjunction with the road construction. So far, 12 ponds are
completed and five more are under construction.
To prevent erosion during construction, a variety of temporary
erosion-control measures are in place. Silt fences, bale checks, bio-logs,
flotation fences, gel floc and rock berms help hold soil in place and keep
sediment out of the state’s public waters.
Piles of construction dirt that aren’t going to be moved or used for 10
days are seeded to grass to prevent erosion. Hughes said construction areas
that are completed are seeded to grass within four to six hours after the
machinery rolls down the road.
A unique system that includes a channel of rocks and liners that cleans
water generated during construction before it’s released into Green Lake was
praised by the U.S. Army Corps of Engineers during a recent inspection. The
corps did, however, find MnDOT wasn’t in total compliance with its permit.
Hughes bristled when asked about a local group, the Lake Region
Preservation Society, which has filed a lawsuit against MnDOT about
construction of the ponds. He said the group has “lost their focus” for
protecting Green Lake and is “raising havoc” with MnDOT out of anger about
the four-lane project.
“Some of the people complaining about it don’t know the facts,” he said.
“MnDOT is more concerned about the environment on this project than I’ve
ever seen them,” said Hughes. “Nobody’s ever taken these kinds of
precautions.”
Hughes said the goal is to contain storm water in the MnDOT right of way
and clean it before it’s released to state waters. “Water going into the
lake looks like this,” he said, holding up a glass of drinking water.
The type of detailed environmental protection and supervision being shown
on the Highway 23 project will become more standard for future MnDOT
projects, said Rasmussen. “We’re definitely going to see more and more of
it.” |
Friday, May 6, 2003
Corps finds noncompliance; MnDOT
says Highway 23 project does follow permit
By Carolyn Lange,
Staff Writer
 |
 |
 |
 |
 |
Tribune
photo by Bill Zimmer
Construction work continues Thursday at the former George’s Food-N-Fuel
site in Spicer along state Highway 23. That site is one location where
storm water retention ponds will be constructed. The U.S. Army Corps of
Engineers says the state Department of Transportation isn’t complying
with a permit for construction of 44 ponds along state Highway 23. MnDOT
disagrees. |
 |
 |
SPICER --
Construction of an 11-mile, four-lane highway through Spicer is not being
done according to the specific requirements of a federal permit, according
to the U.S. Army Corps of Engineers.
Local Minnesota Department of Transportation officials, however, disagree
and say the project is in compliance with the corps permit and that issues
will be resolved with better communication and clarification of verbiage.
Meanwhile, a hearing scheduled for Tuesday in a civil lawsuit filed
against MnDOT on the permit issue, is on hold.
In a letter sent Thursday from the corps, MnDOT was informed that the
agency was “not in compliance with some of the terms and/or conditions” of
the corps’ permit. The primary issue was timely construction of permanent
storm water retention ponds along the corridor.
“Your failure to comply with the permit conditions after agreeing to them
concerns us,” wrote Robert J. Whiting, chief of the corps’ regulatory
branch.
The stern warning came one week after a compliance check was conducted by
two corps officials who were alerted to possible permit noncompliance issues
by a local citizens’ group called the Lake Region Preservation Society.
The corps is giving MnDOT 10 days to submit a plan showing how the
project will be brought into compliance, or face consequences, including
administrative or civil penalties and the possibility of suspending or
revoking the permit. MnDOT could also request modification of the permit.
Representatives from the MnDOT District 8 office in Willmar said they
don’t believe anything is out of order.
Paul Jurek, MnDOT project manager, said MnDOT has a “good working
relationship” with the corps and that the issues can be resolved by
clarifying terms and improving communication with the corps.
Dave Solsrud, assistant district engineer, said the corps had a good
review of the project last week and complimented MnDOT on temporary erosion
control measures, a statement that was reinforced by corps spokeswoman
Shannon Baurer. “They’ve done a good job there,” she said.
As to MnDOT’s claims they are in compliance, Baurer said, “Our regulators
will consider what they have to say.” The corps will return for another
compliance check in a month.
According to the corps letter, MnDOT is not complying with a special
condition to the permit pertaining to the construction of water retention
ponds. Original language required all 44 ponds to be constructed before
roadwork began.
In the same week Lake Region Preservation Society filed its lawsuit
stating MnDOT was not following that permit requirement, the corps wrote a
clarification to the permit stating ponds were to be completed in areas
where road reconstruction had begun.
The corps is now saying MnDOT is not meeting that revised requirement in
the permit and that MnDOT has 10 days to respond.
Jurek said MnDOT is following that permit requirement to build ponds in
drainage areas where roadwork is taking place, just like the special
condition says.
Jim Christensen, MnDOT project supervisor said work is either completed
or under way on ponds being built this year in and south of Spicer, except
for one pond by the Spicer fire hall. He said ponds won’t be built until
2004 in areas where road construction won’t take place until then, which is
an issue that will need to be clarified with the corps.
Jurek said MnDOT also began work this week on construction of two wetland
mitigation areas, which was another point the corps mentioned in the letter.
|
Thursday,
June 5, 2003
Highway 23 costs sewer
district $900,000
By Carolyn Lange,
Staff Writer
The Green Lake
Sanitary Sewer and Water District will be spending approximately $900,000 to
dig up and re-install water and sanitary sewer mains -- including some lines
barely 6 years old -- to make way for the expansion of state Highway 23.
The district, which provides utilities to New London, Spicer and Green
Lake residents, will have to move about a mile of sanitary sewer force mains
and six-tenths of a mile of water mains because those lines lie in the
Highway 23 right of way. A sanitary sewer lift station, just a few years
into its 40-year life span, will be eliminated.
The cost will be difficult for the district to bear, coming on the heels
of higher-than-expected startup costs of the new sewer system, large water
losses from the water plant and yearly rate increases for customers who are
carrying the load of a system that was overbuilt to accommodate future
growth.
“We knew this was going to be a nasty one,” said Gary Danielson,
Kandiyohi County Public Works Director, of the Highway 23-related costs.
“It’s a major impact on us.”
The district intends to pay the bill without raising rates. Instead, the
district will tap into a $450,000 reserve fund and will sell 477 acres of
land that had been used for the old sewage pond and irrigation system, said
Danielson. The sealed-bid sale will take place July 15.
The Minnesota Department of Transportation will pay about $75,000 to move
district mains located on private property, said Danielson. But the cost of
moving lines that are in MnDOT’s right of way is the responsibility of the
utility. It’s the consequence of “being a guest on somebody’s right of way,”
said Danielson.
According to Danielson, it will cost the district $535,000 to move sewer
lines originally installed in 1984 and water lines installed in 1996-97.
Duininck Bros. Construction, the general contractor for the Highway 23
project, was recently awarded the bid for that work.
On top of that, the district funded a $140,000 change order in 1999 to
reroute lines from the Nest Lake bridge area to accommodate the Highway 23
plan and paid $110,000 last fall to move lines out of the right of way in
Spicer. Add engineering costs onto that $785,000 construction fee and the
total cost is about $900,000, said Danielson.
What’s particularly painful is that the water mains from New London to
the Old Mill Road are so new and, in hindsight, could have been installed in
a different location to stay out of the Highway 23 right of way.
Danielson said the lines were laid based on preliminary plans MnDOT had
on locating the four-lane highway to the west of the existing corridor. In
the end, MnDOT opted to shift the highway to the east -- where the
district’s new lines were located.
If he had to do it over again, Danielson said he would’ve held off
installing some of those new lines until MnDOT’s plans were finalized. It
seemed “reasonable” at the time for the county and district to take the
action they did, he said, based on the information they had at the time.
In looking for a bright spot, Danielson said it would have cost the
district considerably more to move the older utility lines if MnDOT had
stuck with their original plan to move the four-lane to the west. If that
had happened, all the sanitary sewer mains from Kandiyohi County Road 30 to
New London would have been relocated and “the bill would’ve been greater,”
he said.
The only difference is that lines installed in 1984 would have been dug
up and replaced, instead of ones installed in 1997. “That hurts,” said
Danielson.
Old sewer ponds for sale
Land north of New London that was used for nearly 20 years for the Green
Lake Sanitary Sewer and Water District’s sewer system is for sale.
The 477-acre piece of property, which is technically owned by Kandiyohi
County, includes three 17-acre ponds where sewage was treated and farm land
that was irrigated with the treated water. Most of the acreage is currently
enrolled in the Conservation Reserve Program and about 30 acres is being
actively farmed.
Gary Danielson, Kandiyohi County Public Works director, said the property
will be sold in parcels, with bids to be opened at the July 15 County Board
meeting.
Efforts are being made to completely pump water from the ponds and remove
a thin layer of sewage sludge from the protective liners on basins, said
Danielson.
He said it’s possible the ponds could be used for fish farming, but that
the liners will likely be damaged during the sludge removal process.
Danielson said the ponds were expensive to construct but couldn’t guess what
they will bring at sale next month.
The property also includes gravel deposits, he said.
The district intends to use revenues from the land sale to offset the
cost of moving water and sewer lines out of the state Highway 23 right of
way. |
Friday, May 30, 2003
Highway 23 project gets
review by Corps
By Carolyn Lange,
Staff Writer
SPICER -- The U.S.
Army Corps of Engineers toured the state Highway 23 corridor Thursday to
investigate whether the Minnesota Department of Transportation is in
compliance with a permit for the $39 million, four-lane project.
The Corps makes periodic compliance checks on construction projects that
were issued Corps permits, but this visit was made at the request of a local
citizen’s group that’s concerned MnDOT may be violating the permit.
The Lake Region Preservation Society notified the Corps earlier this
month that MnDOT wasn’t building the water retention ponds required by the
permit. At the same time, the group was involved with filing a lawsuit
against MnDOT for being out of compliance with the Corps permit and for
violating noise standards. A hearing on those two issues is set for June 10.
Christina Carballal, environmental protection specialist and Jennifer
McCarthy, compliance coordinator with the Corps, spent a couple hours with
representatives from the LRPS and the Green Lake Property Owners Thursday
morning, discussing concerns about the project and touring the construction
zone. They did much the same with Paul Jurek, MnDOT project manager, later
in the day.
The data will be taken back to Corps headquarters and evaluated to
determine if MnDOT is following the permit, said McCarthy. No decision is
expected this week, but it doesn’t appear likely that MnDOT violated a key
permit condition that caught the attention of the LRPS.
Pat Laib, LRPS member, said not only had MnDOT not installed all the
ponds along the 11-mile corridor, but pond construction hadn’t begun in
areas where the new roadbed was already being constructed. Laib said a day
or two after the lawsuit was filed, crews began building the ponds.
Carballal said the Corps didn’t intend that all the ponds had to be
installed first, before any road work began. McCarthy said the “reasonable”
approach is to construct the ponds as road crews advance down the corridor.
A letter of clarification from the Corps to MnDOT said ponds should be
constructed “before the start of earth work in its respective drainage
areas.”
Laib said what matters most is that MnDOT is doing the project correctly
and in a fashion that protects Green Lake and the watershed. |
Saturday, May 24, 2003
Keeping MnDOT accountable: Local
group files complaints on Highway 23 project
By Carolyn Lange,
Staff Writer
SPICER -- Members of
a local watchdog group that filed a complaint against the Minnesota
Department of Transportation this month on the Highway 23 four-lane
construction project said they don’t want to go to court, they just want the
project done right.
The complaint cites a possible violation of the Army Corps of Engineers
permit that was issued to MnDOT, and says that a breach of traffic noise
standards needs to be abated.
The Lake Region Preservation Society, along with a Spicer couple, Ron and
Betty Schneider, filed the complaints May 6.
They hope to draw attention to the construction problems -- and
correcting them -- said Pat Laib, LRPS member.
As it stands now, the case is scheduled for a June 10 hearing in Willmar.
One of the complaints states that MnDOT is violating its permit from the
Army Corps of Engineers. That permit required MnDOT and the contractor,
Duininck Bros. Construction, to build 44 water retention ponds along the
11-mile corridor before roadwork on the highway began.
A May 8th letter to MnDOT from Robert Whiting, chief of the Corps
regulatory branch, says the Corps “would expect” the storm water management
basins, infiltration basins or grit chambers proposed for each drainage area
“be constructed before the start of earth work in its respective drainage
areas.”
Whiting wrote that the letter was due to “recent public concerns brought
to our attention” regarding the Highway 23 project and MnDOT’s permit for
the project.
Laib said as soon as that letter was received, work was accelerated on
the holding ponds. “Things are really boiling now,” he said. “We just want
to make these guys do what they’re supposed to do.”
Construction crews did not install all the holding ponds along the
corridor before beginning road work, but progress is being steadily made on
constructing the ponds, according to MnDOT.
In an interview in December with several MnDOT officials, it was stated
that constructing the ponds would take place sequentially, as the road
construction moved down the corridor.
A representative from the Corps is expected to tour the construction site
on Thursday. “If they tell us everything here is fine and dandy, then we’ll
go away,” said Laib, at least on the water retention issue. “But if you ruin
the lake by not doing this thing properly, you get your road but you lose
your lake.”
The second complaint the LRPS and Schneiders have filed pertains to
studies that show traffic noise on Highway 23 will exceed Minnesota
Pollution Control Agnecy standards.
MnDOT conducted an initial study as part of its construction plan that
showed noise levels already exceed standards and that the levels will be
exceeded even further in the future in some areas. Then, last year,
Schneider asked the Spicer city council to request MnDOT do another noise
study. The council agreed, and MnDOT conducted a second study at a cost of
about $75,000.
The results of that study, which were presented to the Spicer city
council earlier this year, indicated noise levels in four areas along
Highway 23 in Spicer would exceed MPCA limits. It also showed that, under
the federal financial benefit criteria, three of the areas didn’t qualify
for construction of noise walls, said Lowell Flaten, MnDOT project engineer.
The one area that would qualify is in a commercial area where tall noise
walls wouldn’t be desirable.
Flaten said MnDOT is asking for an exemption from meeting the MPCA noise
standards. A final ruling on that is expected to be made this fall by the
heads of MnDOT and the MPCA.
Regarding the legal complaint, Flaten said it’s “somewhat of an unusual
suit.” He said there are no noise walls in this MnDOT district. If it’s
decided noise abatement needs to be done, Flaten said walls can be
constructed after the highway is completed.
Laib said the LRPS “doesn’t want to stop a road” from being built and its
goal isn’t to go to court. If the judge would rule in their favor, he said
the citizens would have to put up a bond worth 10 percent of the $39 million
project. “I’m a little short of $3.9 million,” said Laib.
He said he hopes the complaints will help protect Green Lake and hold
MnDOT accountable. He said the LRPS was given the task of holding MnDOT’s
feet to the fire with the project, and members intend to do that.
|
Public Forum,
Thursday, May 22
|
Help keep your grass at home
To the Editor:
“Spring Has Sprung” … and new life is all around us … fresh new growth
of trees and plants, new roads and landscapes and wonderful new homes …
all within Kandiyohi County and our beautiful lakes and water ways.
But along with spring clean-up, we are seeing people using road
ditches, streets and roads as their personal dump sites! Why?
Let us start “a-new” and with personal pride … keep our beautification
project all around Kandiyohi County. Let us “begin a new” with yard refuse
being taken care of properly and keep beautiful Kandiyohi County lakes and
water ways beautiful!
Grass clippings have large amounts of phosphate within them. When you
mow your lawn, we would like to suggest to you that the first four rounds
of mowing turn the grass clippings into your lawn. This will benefit your
lawn by the phosphate, within the clippings, and it will not find its way
into our water system.
When grass clippings are blown on the street level, rain water will
wash them into the storm sewer which will find its way to our lakes and
waters of Kandiyohi County. One pound of phosphate “may” produce up to 400
pounds of algae/weeds within our lakes and rivers.
Be a good naturalist, a great ecologist by blowing your lawn clippings
onto your lawn. It protects our water plus it fertilizes your lawn! We all
win!
Terry W. Frazee
Executive Secretary
Green Lake Property Owners Association
Spicer |
Thursday, May 22, 2003
Spicer council
scrutinizes construction bill
SPICER -- A lengthy
$640,000 bill for utility work that was scrutinized by the Spicer City
engineer turned up questions on how much the city is being charged for a
couple line items.
At the Spicer city council meeting Wednesday, Randy Sabart said there
were several discrepancies in the bill that could have the city paying more
than their share for several segments of water and sewer pipes.
Sabart estimated the questionable charges at about $20,000. He said he
believes the Minnesota Department of Transportation may be responsible for
those costs.
While the state Highway 23 four-lane project is underway, the contractor
is also replacing water and sewer lines for the city. Some parts of the
project are being shared by MnDOT and Spicer and some are the responsibility
of the separate entities. MnDOT is in charge of splitting out the costs for
the city, which is where Sabart identified some possible miscalculations.
The council agreed to make the payment in order to meet the deadline and
avoid a penalty, but will include a cover letter calling attention to the
areas of question. Mayor Bill Taylor said a final settlement at the end of
the project will rectify any cost adjustments.
Of the $640,000 bill, City Administrator Kim Wothe said about $610,000 is
for the city utility work and $50,000 is the city’s cost associated with the
Highway 23 project.
In other action the council:
- Agreed to set up a joint meeting with the Green Lake Property Owners
to cooperate on plans to improve the water quality of Green Lake.
- Agreed to spend $125 to spray the city parks for tent caterpillar
worms, as part of efforts initiated by the Green Lake Property Owners
Association.
- Approved permits for the July 4th activities.
|

LAKE
AVENUE TO REOPEN IN SPICER
05/22/2003
The Minnesota Department of Transportation says they
plan to reopen a portion of Lake Avenue in Spicer Thursday afternoon.
Construction Engineer Paul Jurek says Lake Avenue will remain gravel for about
another week-and-a-half until crews pave and install curb and gutter. It's been
closed since Mid-April so crews could install new water and sewer mains. Similar
construction will take place on Country Road 10, Ruth Street, between Highway 23
and lake Avenue. It will be necessary to close that area and traffic will be
routed through downtown Spicer.
Thursday, May 08, 2003
Spicer may request audit of
GLSSWD
By Carolyn Lange,
Staff Writer
SPICER -- Frustrated
by water rates that have doubled and sewer rates that have tripled in the
last three years, the Spicer city council may request a financial
investigation of the Green Lake Sanitary Sewer and Water District.
Spicer Mayor Bill Taylor said Wednesday during the council meeting that a
state audit of the GLSSWD may be necessary. Councilwoman Marlys Larsen
quickly agreed.
Even the city’s auditor, Paul Harvego, who was presenting the 2002 audit
report, encouraged the city to question the GLSSWD’s fees.
In his written report, Harvego said a review of the utility fees billed
by the county “indicate a need to question why these costs have more than
doubled over the past three years.” He wrote, “these increases have far
outpaced the current revenue stream” and will result in a negative cash flow
unless the costs are stabilized.
The city’s sewage treatment charges increased $100,000 from 2001 to 2002.
GLSSWD, which sells water and sanitary sewer services to Spicer, New
London and Green Lake residents, has repeatedly changed the fee formula for
the entities in recent years, said Taylor.
Some of the added costs that are passed on are because of operational
problems with system, including an estimated 60 percent water loss in the
brand new water mains around the lake. Another cause for the rate increases
is because of a “$5 million cost over-run” for the project, said Councilman
Terry Holmquist.
Larsen asked if Kandiyohi County shouldn’t bear some financial and legal
responsibility for the GLSSWD’s financial troubles. She said the plant was
overbuilt and only one-third of the system is being used, yet current users
are paying 100 percent of the cost.
The council agreed to hold a public hearing June 4 to request a one-year
extension from the Minnesota Department of Trade and Economic Development
for a revolving loan issued to the city on behalf of Marketing Concepts.
The business, which was affected by the Sept. 11 attacks, was unable to
meet it’s criteria for adding a required number of new jobs, said Jean
Spaudling, Spicer Economic Development Authority director.
Because of expansions of the business that utilized the $189,000 DTED
loan, Spaulding said Marketing Concepts will be able to meet the criteria by
adding 30 new jobs, but it won’t be done by the May deadline.
If the extension isn’t approved, Marketing Concepts would have to forfeit
loan money and the city wouldn’t be able to utilize the revolving loan
money. The city wouldn’t lose anything, said Spaudling, it just wouldn’t
receive revolving loan money it was expecting.
In other action the council:
- Approved a tax increment financing agreement with Bluebill Inc. for
construction of the new United Prairie Bank on the south edge of Spicer. A
final plat for the bank property was also approved.
- Was informed that a leak in the water main on Lake Avenue South was
repaired. The main had been leaking about one million gallons a month.
|
Wednesday, May 07, 2003
Merger fails: Referendum defeated in two of three communities
By Carolyn Lange,
Staff Writer
 |
 |
 |
 |
 |
Election
Judge Sandy Saulsbury checks the registered voters list Tuesday for
Lorene Kempthorne’s name at the New London Township Hall. |
 |
 |
A proposal to
merge New London, Spicer and New London Township into one new city was
soundly defeated Tuesday in a special election. A majority of voters in two
of the three jurisdictions cast ballots against the referendum, killing the
proposed consolidation plan.
New London was the only entity to approve the proposal. It passed there
with a 41-vote margin, on a vote of 153-112.
The referendum failed in Spicer by a 90-vote margin, on a vote of
220-130.
The largest defeat came in New London Township where the proposal was
trounced on a vote of 1,125 to 160 -- a 965 vote margin.
“We did our job. We put it forth. The people have spoken,” said Denny
Baker, chairman of the merger task force, after the ballots were tallied.
Baker, of Spicer, had worked with representatives from the three
communities for the past two years studying the pros and cons of merging the
36-square mile area into one new city called New London Spicer. The task
force had recommended approval of the merger and the city councils and town
board had agreed to bring the issue to the voters.
“This was something that was explored and the governmental bodies
authorized us to move ahead,” said Baker. “We put it together and people
have spoken, we can say no more than that.”
Voter turn-out in both the cities was 46 percent. In the township, 65
percent of registered voters cast ballots, a little lower than the average
for a general election. By 10 a.m. 400 people had voted in the township,
compared to about 80 in Spicer and 70 in New London. Around 5:30 p.m.,
people were standing outside the town hall, waiting to vote.
The overwhelming vote against the measure in the township was indicative
of the message township residents had been repeating since the proposed
merger was first discussed.
Township residents attended informational meetings in large numbers
during the course of the two-year study, whereas only a handful of city
residents ever showed up for the meetings.
Some of the concerns township residents reiterated were increased taxes,
concern about losing hunting rights and other zoning issues, water and sewer
expansion, debt of the cities and fair representation on the city council.
All that a merger would do is “create a large bureaucracy for the
politicians,” said Brian Nelson, a township residents, after he cast his no
vote at the town hall. He said he hoped the issue would be defeated by a
large enough margin to “stamp it down hard” and discourage a similar
referendum in the future.
Nelson said he hadn’t talked to anyone who supported the referendum. “It
was kind of a folly to start with,” he said.
What now?
The idea to pursue a merger took hold in 2001 as a way to stall hostile
annexation proceedings initiated by the New London city council. The
council, led by Mayor John Mack, sought to annex 96 parcels of developed
residential and commercial property through involuntary annexation. When the
township residents and town board objected, consolidation was offered as an
alternative.
Now that consolidation has been rejected, Mack said the city will pursue
annexation.
This spring the city signed an agreement with the township to put a
one-year moratorium on involuntary annexation while the two entities pursue
discussions of orderly annexation in “good faith.”
Mack said the city will negotiate with the township and said he hopes the
discussions are sincerely carried out “in good faith.” But Mack said the
city will likely seek annexation of the same 96 parcels that were initially
pursued. He said the annexation could be accomplished gradually through
orderly annexation but the city wasn’t going to walk away without getting
something.
Mack said the vote Tuesday by New London residents to approve the merger
is a mandate from city residents to pursue “a program of annexation.” The no
vote by township residents indicates the township “isn’t interested in
alternatives,” he said.
Without a merger, Spicer Mayor Bill Taylor said annexation will be
pursued by both cities. He said the merger “was an idea that was brought
forward and I still think the idea was good.”
He said taxes will go up in all the entities, with or without the merger,
because of state budget cuts and decisions on how the cities “move forward”
will depend, in part, on what financial action the Legislature takes.
Even though the merger failed, Taylor said he still considers the area as
one community, because it shares a school district and other community
programs.
Despite the defeat, Mack said the merger study and election was a
fruitful exercise because it created a “road map” for future development for
the community.
Township voters
People voting in the township didn’t come into the polls talking about
the issue, “but people are very serious and determined,” said Howard
Patrick, election chairman, during an interview in the morning. “They’re
motivated. Interest is high and turn-out is terrific.”
James Leipold, a township resident who lives on the edge of the New
London city limits, didn’t waste much time voting. He said he didn’t bother
going into the privacy booth but simply put a check-mark by the “no” and
“dropped it in the can.”
He said he has a new well and septic system and has no need for city
services. Leipold said his property, along with 95 other parcels, was
targeted for annexation when New London initiated a hostile annexation
procedure two years ago. He said he was counting on the township to fight
any future attempts by the city to annex his and his neighbor’s property.
“I’m very pleased there’s such a good turn-out. It shows the interest is
high,” said Sandra Nelson, a township resident. She said she voted against
the merger because of concerns about representation, lack of input on
development issues, local costs associated with the state Highway four-lane
project, as well as other issues.
“I’m very upset with it. It’s taking away our freedom,” said LaVonne
Lundebrek, who lives on Nest Lake. “We didn’t choose to live in New London.”
Lundebrek said everyone’s she’s spoken to was planning to vote against the
merger. “We’re all voting no. I haven’t talked to anyone who’s in favor of
it, even the people in New London,” she said. “We know which way it’s going
to go.”
“We’re hoping that the consolidation does not go through. We live in a
rural area and we want to keep it that way,” said Brian Nelson.
Only one township resident told the Tribune he’d voted for the merger. “I
think it’ll be good for all three,” said Arnie Liestman, a soft-spoken
elderly gentleman.
He said the positive aspects included having one government and having a
large enough population to qualify for additional funds. Towns with a
population of 5,000 or more are eligible to receive state transportation
money to build and maintain roads. “I think it’s a good deal,” said Liestman.
“I think it’s going to go.”
City voters
Through much of the two-year process, city residents had been pretty
quiet on the merger issue, and that followed through on Tuesday. Everyone
the Tribune asked for comments in an exit poll in New London and Spicer
declined to comment on record.
Until just days before the election there’d been no public campaigning on
the issue. Signs encouraging people to vote against the merger started
popping up this weekend. The signs were reportedly made and erected
primarily by Spicer residents. |
Wednesday, April 23, 2003
Expect delays on Highway 23
 |
 |
 |
 |
 |
Terry
Samuelson, left, and Kerry Nelson of Prinsburg Sodding and Seeding
stretch a floating silting curtain along a slough Tuesday near State
Highway 23 in Spicer |
 |
 |
WILLMAR --
Motorists will encounter delays on State Highway 23 due to the installation
of new work zone safety devices and an increase in related construction work
between the junction of State Highway 71 and the city of Spicer, according
to officials at the Minnesota Department of Transportation.
Paul Jurek, MnDOT construction engineer, said work crews should finish
installation of concrete jersey barriers in two locations sometime today.
The barriers will be installed in Spicer and east of the Kandiyohi County
Road 9 junction. The barriers are necessary to keep traffic away from the
excavation of the new roadbed. Traffic will be reduced to one lane during
the installation.
Motorists are advised to slow down in the work zone and to watch for
trucks hauling materials to and from the construction areas. MnDOT also asks
motorists to consider an alternative route.
Jurek also said crews will begin widening the highway at the 71/23
junction this week. Traffic will be reduced to one lane during this
construction and motorists are asked to slow down and watch for flaggers.
MnDOT is urging motorists to consider using an alternative route around
construction zones this summer. When it is necessary to travel in a work
zone, MnDOT workers and contractors ask that motorists slow down, focus on
their driving, stay alert for workers and equipment and never enter a
roadway that has been blocked with barriers or cones.
A majority of the 11-mile project is expected to be completed in 2004 but
work may extend into 2005. The total price tag for the project is estimated
at $52 million, including $39 million for construction and $13 million for
the purchase of right-of-way. Duininck Brothers Construction of Prinsburg is
the general contractor for the project.
For information related to the Highway 23 four-lane project, log on to
the project Web site at
www.dot.state.mn.us/d8/projects/23.
|
Thursday, March 06, 2003
MnDOT advises
businesses to work together during Highway 23 construction
By Carolyn Lange,
Staff Writer
 |
 |
 |
 |
 |
Jim
Christensen, Senior Engineering Specialist with MnDOT, answers questions
after the meeting. |
 |
 |
SPICER -- As
contractors prepare to begin the four-lane reconstruction of state Highway
23 through Spicer, businesses along the corridor are being advised to be
proactive during the two- to three-year construction period.
During a meeting Wednesday with the Minnesota Department of
Transportation in Spicer, about 35 local business owners and managers were
encouraged to participate with a MnDOT program called “In this together.”
The program emphasizes communication between contractor Duininck Bros.,
MnDOT, local businesses and customers.
The key to keeping customers coming to businesses during a major highway
project, said Sandy East, public relations director from the Willmar MnDOT
office, is for businesses to work together to create a cooperative plan for
signage, advertising and special promotions.
A workbook that walks business groups through a plan of action includes
ideas like holding special “hard hat” promotions to draw attention to the
community, developing cooperative advertising campaigns, scheduling
ground-breaking ceremonies at the beginning of the project and
ribbon-cutting ceremonies at the end.
“We want to help your business survive,” said East.
One point businesses will want to emphasize during the construction of
the new four-lane highway is that traffic will not be detoured around town,
said Jean Spaulding, Spicer’s economic development director. Highway 23 will
be open for traffic through Spicer during the entire construction project,
according to MnDOT.
That doesn’t mean the traffic will always run smooth and easy, said Lee
Duininck, but traffic will not be diverted away from Spicer businesses.
Jim Christensen, senior engineering specialist with MnDOT, said the
existing two lanes of Highway 23 will be used to carry traffic while the two
new lanes are being built.
Besides letting customers know that their businesses will be open and
accessible during the project, East also said it’s important that businesses
communicate with their suppliers about the construction schedule to make
deliveries easier.
Christensen said if MnDOT and the contractors are notified in advance
about special events businesses have scheduled, certain construction can be
avoided in that time and place. “We can work around that,” he said. “Let us
know. ... It can save a lot of headaches.”
Aside from Our Lady of the Lakes Catholic Church, there were few
questions about how the highway construction would affect specific
businesses. The congregation is in the process of building a new church,
which won’t be completed until later this summer. Preliminary work on a
roadbed on the church property, however, needs to begin this spring to meet
the timeline.
Other questions dealt with moving power lines, water and sewer mains and
construction of the new Nest Lake Bridge.
Spaulding said she will work with the Spicer Commercial Club to
coordinate the MnDOT program with businesses in Spicer and New London. “This
gets us off on the right foot,” she told the group at the close of the
meeting.
Depending on the weather, construction could begin in early April. The
initial construction will be at the junction of Highways 23/71; and creating
a frontage road by Kandiyohi County Road 9; and reconstruction of streets
and development of a water retention pond at the Food-n-Fuel site in Spicer,
both of which are expected to be completed by July 4. |
Thursday, March 06, 2003
Annexation agreement forged between New London, township
By Carolyn Lange,
Staff Writer
NEW LONDON -- In a
move that could be called either good strategy or blackmail, New London
Township has secured a signed agreement from the New London City Council not
to pursue involuntary annexation for 12 months if a proposed merger between
New London, Spicer and New London Township fails.
The agreement was approved by the New London city council on a 3-1 vote
Wednesday. Mayor John Mack voted no. Council members Bruce Nelson, John
Bergman and Margaret Pederson voted yes, although Pederson’s vote was cast
reluctantly.
Held hostage was a request for the orderly annexation of 40 acres of land
northwest of New London, where developer Dan Binsfeld is ready to begin
construction of a residential development.
Merle Gjerde, chairman of the New London Town board, appeared before the
city council asking that the city make a commitment to “sit down and talk”
about orderly annexation if the merger fails.
If the city wouldn’t sign the agreement he had in hand, then the township
wasn’t likely to approve the annexation of Binsfeld’s property, he said. If
the city approved the agreement, then the Binsfeld annexation would be
approved by the township.
“This is terribly, terribly unfair of you to put Mr. Binsfeld in the
middle of this,” Pederson told Gjerde.
Mack said it was inappropriate to discuss possible action the city would
take if the merger vote failed before the vote was even taken.
He said agreeing not to involuntarily annex property if the merger failed
would send “mixed messages” and could “jinx the merger.”
Binsfeld, obviously frustrated by the political tic-tac-toe, said he had
other projects to work on elsewhere and that the New London could be delayed
for years if the entities couldn’t come to an agreement.
Mack said the township was holding a “gun” to the city’s head.
“Now you know how we feel,” responded Gjerde, referring to the city’s
efforts to forcibly annex nearly 100 parcels of residential and commercial
township property two years ago, action that eventually led to the merger
study.
“We just need something in black and white,” said Gjerde. “We need to
talk.”
Gjerde said he has asked the city council repeatedly in the past to
discuss orderly annexation issues, but nothing has ever happened. Signing
the agreement, which asks that the two entities “work in good faith,” would
help the entities lay out a reasonable plan for orderly and timely
annexation.
Pederson said she was more than willing to talk with the township about
annexation, “but there will be action as well,” adding that the city could
have already absorbed township lots through contested annexation.
“We just need to get along,” said Nelson.
Bergman, who is on the merger task force, agreed. “We do need to sit down
and talk,” and if a “handshake” isn’t enough, then the council should
approve the township’s request, he said.
The township’s original agreement called for a time frame of 18 months
that the council wouldn’t see contested annexation. That was negotiated down
to 12 months.
If the merger is approved, the agreement would be unnecessary. The
document also says the agreement would become null and void “if either party
refused to work out a plan or reasonable progress is not being made on the
plan.”
Resolution for vote on merger approved
In three separate votes Wednesday night, the governing bodies of three
local entities agreed that a referendum to merge into one new city should go
to the voters.
The city councils of New London and Spicer and the supervisors for New
London Township voted unanimously at their separate meetings for a
resolution calling for the vote on May 6.
A task force has been studying a proposal to merge for nearly two years
and recently presented a final consolidation plan to residents.
The question on the ballot will ask voters if the three entities should
“consolidate to form a single municipal corporation of the State of
Minnesota, pursuant to the consolidation plan on file with each of the
cities and the township, and shall the proposed new charter be adopted.”
A majority of voters from all three entities must vote yes in order for
the merger to be approved. If a majority of voters in one entity votes no,
the merger will not take place.
If approved, the new city limits would encompass all the property in New
London, Spicer and New London Township. A transition board, comprised of the
existing city council and town board members, would be in power until a new
seven-member city council is elected in November from four wards from the
new city. The new council members would take office Jan. 1, 2004.
The formal resolution calling for the vote said that the governing bodies
“approves” of the final plan of consolidation. The wording of that
resolution was approved by the city councils without discussion.
The town board agreed to “accept” the plan and call for the vote. “We
accepted the plan and want it to go onto the voters,” said Merle Gjerde,
board chairman, “But we’re not formally saying we’re for it or against it.”
|
Thursday, March 06, 2003
County plans 2003 overlay work
By Linda
Vanderwerf, Staff Writer
WILLMAR -- Kandiyohi
County plans road projects worth an estimated $5.4 million this year.
County Public Works Director Gary Danielson said he hoped oil prices
would have fallen by the time bids on the first major road contract are
opened in early May. The County Board met Wednesday morning to discuss
public works issues.
Estimates were increased about 20 percent to account for rising oil
prices, he said.
The county will resurface and make other improvements to nearly 35 miles
of county roads this year. The projects will use an estimated $2.6 million
in state aid funding.
Renville County will pay more than half the cost of an overlay on County
Road 1 near the county line. The city of Willmar will pay part of the cost
for improvements to County Road 24 east of County Road 5 near Ridgewater
College.
Danielson said he had scheduled work on County Road 4 on the east side of
Green Lake for later in the year but now wants to delay it. Rather than do
some road work this year and then replace the bridge on it a year later,
Danielson suggested doing the entire project at the same time, beginning
after Labor Day in 2004.
The delay would also help cut down on the number of detours in the Spicer
area at the same time, Danielson said.
“We can do it after Highway 23 is pretty well built if we do it in 2004,”
he said.
A “thin overlay,” about one inch of blacktop, will be done on several
roads which are still in good shape except for some rough joints and slight
ruts on the driving surface, Danielson said.
“We think they’re going to last a long, long time,” he said.
The board decided to move ahead with two recommendations to make the
rights of way along county roads safer.
In rural areas, some farmers have expanded their fields into the right of
way, damaging ditches and field approaches.
In some cases, “they’re plowing right to the road,” said Commissioner
Harlan Madsen. “There’s no ditch anymore.”
Land owners will be contacted and the county will repair and reseed road
ditches where needed, Danielson said.
Commissioner Richard Falk asked if the effort would extend to lake
property.
“We will go after them all, but we’d like to start out with a priority of
the worst ones,” Danielson said.
The worst cases are in rural areas, he said, and he will be sending
notices before crops are planted.
Mailboxes along county roads are also a concern, Danielson said. Some
boxes are on heavy posts or other structures that present a safety hazard.
State law says mailboxes should be placed on swing-away posts, or on
4-inch wooden or 2-inch metal posts. The idea is to have a post that can
stand up to snow thrown by snowplows but which will break away when struck
by a vehicle.
The board voted to replace mailbox posts with the swing-away type after
county road projects and to contact owners of other mailboxes that do not
follow regulations. Danielson will present a written mailbox policy at the
April 1 meeting.
In other business, the board:
- Voted to add $5 an hour to rates townships pay to have the county blade
gravel roads and plow snow. The new rate will be in effect back to March 1.
“The day of giving things to other people free is coming to an end,” Falk
said.
- Voted to add 15 percent to the actual cost of materials or engineering
services provided for another unit of government. The charge is to cover
administrative overhead. |
Friday, February 21, 2003
Meetings on merger
scheduled for Tuesday
Meeting Preview
Public information
meetings to discuss the proposed merger of New London, Spicer and New London
Township will be held Tuesday.
A task force has recommended that the three entities merge to create one
new town. A referendum is set for May 6. A series of meetings will be held
in the next couple months to inform residents about the consolidation plan.
During a nine-hour span of time Tuesday, four different merger meetings
will be held.
Small group meetings will be held in each of the communities Tuesday
afternoon to provide residents with an opportunity to have a one-on-one
discussion with the merger consultants and task force members.
A community meeting for residents of all three entities will be held from
7-9 p.m. Tuesday at the NLS High School in New London.
Residents in Spicer can come to the Spicer City Hall between noon and
1:30 p.m. to meet with consultants Rusty Fifield and Dean Johnson,
Councilman Terry Holmquist and merger task force members Denny Baker and
Aaron Butler.
New London Township residents will meet from 2 to 3:30 p.m. at the
township hall. Besides the consultants, township supervisor Mark Mertens and
task force members Greg Hedman and Sarah Lewis will be on hand to answer
questions.
In New London, residents are invited to the City Hall between 4 and 5:30
p.m. to discuss the merger with the consultants, council members Margaret
Pederson and John Bergman and task force member Jane Benson.
A general public meeting will be held from 7-9 p.m. for residents from
all three communities. That session will be held at the NLS High School
cafeteria.
On Feb. 27, the New London Township board is expected to vote on a joint
resolution calling for a public election on the consolidation plan. The New
London and Spicer city councils are expected to take similar action at their
meetings on March 5.
Additional public meetings will be held in March and April. The merger
election day is set for May 6. Residents from all three communities must
vote yes for the merger to be approved. If the majority of residents in one
community vote against consolidation, the merger will not take place.
|
Thursday, February 20, 2003
Spicer council
prepares for Highway 23 construction
By Carolyn Lange,
Staff Writer
SPICER -- The city
of Spicer is preparing for construction on state Highway 23, a project
that’ll disrupt traffic through town for two years.
Construction of the four-lane route is expected to begin in April.
The council was informed Wednesday that the Spicer Economic Development
Authority will hold a meeting in March with the local businesses and the
Minnesota Department of Transportation to discuss issues about handling
traffic during the project.
The meeting will lay out issues to help businesses work through the
construction process through a MnDOT program called “In this together,” said
Jean Spaulding, Spicer Economic Development Authority director.
Mayor Bill Taylor said even though traffic will still go through town
during the entire construction project, there will be “inconveniences” that
businesses and residents will have to deal with.
According to MnDOT, construction crews will begin work the first week of
April, weather permitting. Preliminary work before that time will consist of
removing buildings along the 11-mile route, which stretches from the
junction of U.S. Highway 71 south of Spicer, to Kandiyohi County Road 31
north of New London.
The $37 million construction project, which is estimated to run $52
million when right-of-way purchases are factored in, will begin at the south
end, at the junction of Highway 71. At the same time, construction will take
place at the Food-N-Fuel in Spicer. The business is being removed to make
way for a wider street and a water retention pond.
A frontage road will be built to carry traffic during construction of a
new overpass bridge at Kandiyohi County Road 9, but traffic will not be
detoured around Spicer during the project.
Meanwhile, the council approved a resolution supporting the funding and
construction of a four-lane highway on state Highway 23 from Willmar to St.
Cloud. The resolution will be part of a package of information requesting
federal funds for the Paynesville four-lane segment.
A group of areas community leaders will be appearing before Congressional
delegates next month to ask for special funding to accelerate the
Paynesville segment of the Highway 23 corridor four-lane project.
The resolution doesn’t recommend where the four-lane should go in
Paynesville, but only that the four-lane corridor should be built.
Paynesville residents are still weighing the pros and cons of keeping
Highway 23 through town on the existing route, or developing a new bypass.
In other action the council:
- Discussed possible effects of Gov. Tim Pawlenty’s budget-reduction
proposal.
- Tabled action on selling the old fire hall property even though a
purchase agreement for the advertised price of $80,000 had been offered.
The council agreed to take more time to reconsider how to sell the
property and what kind of development would best serve the city.
- Agreed to pay the full amount of $1,600 for construction last fall of
a temporary drainage ditch in a business area of Progress Circle. The
council had earlier agreed to pay half the cost, with property owners
picking up the rest. Only one business owner agreed to contribute to the
project, however.
- Approved a resolution to allow charitable gambling at G. Michael’s
Restaurant, sponsored by the West Central Snow Drifters snowmobile club.
Final approval is required by the state.
|
Thursday, February 20, 2003
Highway
23 project awarded; construction begins in April
By the Tribune
Staff
WILLMAR -- The
Minnesota Department of Transportation has awarded a $37.9 million contract
to Duininck Bros. Construction of Prinsburg for the state Highway 23
four-lane project through Spicer.
The company was the apparent low bidder when proposals for the project
were opened in December. After reviewing the bid, the MnDOT District 8
office in Willmar announced this week it has officially awarded the contract
to Duininck Bros.
The project includes the expansion of Highway 23 to four lanes between
junction of U.S. Highway 71 and County Road 31 north of New London.
According to Paul Jurek, MnDOT construction engineer, crews will begin the
first week of April if weather permits.
Preliminary work will consist of building removal along the entire
project. The reconstruction of the highway will begin simultaneously at the
Food-n-Fuel in Spicer and at the south end of the project at the junction of
Highway 71. A frontage road will be built to carry traffic during the
construction of the new bridge at County | |